Touchtop Technologies, Inc.

TIME LINE

Milestone

Target Date

Status

Concept Development – Functional Specifications –LEDCD

October 1993

Complete

Detailed Design – LEDCD

January 1996

Complete

Breadboard

February 1996

Complete

Functional Specifications – Display Driver Code

February 1996

Complete

Functional Specifications – Intelligent Driver Editor

February 1996

Complete

Detailed Design – Display Driver Code

June 1996

Complete

Detailed Design – Intelligent Driver Editor

June 1996

Complete

Testing – Display Driver Code and Intelligent Driver Editor

July 1996

Complete

Tentative Commitment From NEEC

March 1996

Complete

Detailed Design of Manufacturing Components/Reetooling

October 1996

In Process

1st Round Funding

January 1997

Open

Full Scale Prototypes Constructed

June 1997

Open

Testing, Q & A and Documentation

September 1997

Open

Agreement With NEEC Finalized $25 Million

January 1998

Open

Two $25 Million Licenses Executed

January 1999

Open

One $50 Million License Executed

January 2000

Open

First Royalties Realized

January 1999

Open

Next Generation Screen/Interface Development Completed

September 2001

Open